2018/19 road resealing programme to commence

Add to favourites

Every summer Council undertakes its road resealing work. Roads require resealing for a number of reasons including when cracks or potholes start to appear, or they become slippery.


Resealing works are undertaken during summer as the hot weather is needed for the mixture to set, with the resealing process usually taking up to five days to complete.

The first stage of the 2018/19 reseal programme begins on the 11 December 2018. The streets being resealed in stage one are:

Road Name Approximate Start Approximate End Total Length
BEACONSFIELD ROAD 
CLIMIE ROAD 
DENBIGH ROAD 
GLANVILLE ROAD 
KAHOURI ROAD 
MANGAPAPA ROAD 
PALMER ROAD (SOUTH OF OPUNAKE ROAD) 

Properties affected by stage one of the resealing work will have received notification from Council’s contractors Inframax or Higgins.

Vehicles travelling in these areas are asked to reduce their speed to avoid the risk of the resealing chip being flicked up from the road surface.

If you have any questions or issues please phone Council’s Service Centre  on (06) 765 6099.